Published September 27. 2025 09:24AM
• Start date: Feb. 12, 2026.
• Completion date: 2030.
• Project area: A 3.5 mile section from Exit 303 (Ninth Street, Stroudsburg) to Exit 307 (Park Avenue/Route 611 to Broad Street/Route 191, Stroudsburg business district).
• Work to be done: 12-foot wide travel lanes, 12-foot shoulders on both the inside and outside shoulders, and longer acceleration and deceleration lanes.
• Cost: $935 million.