Officials tour Northface project site
The Northface Project at the former New Jersey Zinc Co. West Plant in Palmerton is drawing renewed scrutiny as its Pennsylvania Department of Environmental Protection permit approaches expiration in June 2027.
DEP Secretary Jessica Shirley recently toured the 120-acre site along Mauch Chunk Road off Route 248 with state Rep. Doyle Heffley, R-Carbon, DEP officials, Palmerton Borough representatives and staff from state Sen. David Argall’s office.
Heffley and Argall requested the visit following complaints from residents about odors, overweight trucks, increased truck traffic and road damage near the site.
“Our residents deserve to have their concerns heard and addressed,” Heffley said. “While cleaning up this former industrial site and preparing it for future use is important, that work must be done responsibly and in compliance with environmental regulations.”
Heffley said conditions at the site had improved for a period but concerns have intensified again.
“The concerns about strong odors, overweight trucks and uncovered loads needed to be addressed, which is why Sen. Argall and I requested that DEP visit the site firsthand,” he said.
The tour included DEP Northeast Regional Director Joseph Buczynski and Roger Bellas, waste management program manager for DEP’s Northeast Region.
Following the visit, Heffley said that state officials reviewed DEP’s plans for addressing complaints tied to the project.
“There have been many concerns regarding the fill being brought into the site,” he said. “I was able to see the plan to make sure there are processes in place to address future issues.”
Argall said the visit gave DEP officials an opportunity to see local concerns firsthand. “My office will continue to monitor the project and ensure that the concerns raised by Palmerton residents are addressed,” Argall said.
Community concerns
Save Carbon County has been protesting the project, urging Palmerton Borough Council to oppose renewal of the permit. The group is scheduled to meet with DEP officials Nov. 13 in Wilkes-Barre to discuss concerns and DEP oversight.
During a September site tour with Rich Parrish of Impact Environmental, group members reported noticing strong odors. Save Carbon County President Linda Christman, members Londa Ritchey, Kathy Fallow and Cathy Mueller, and Palmerton Municipal Authority representative Jonathan Siller attended the tour.
Ritchey said the group’s goals are ensuring the project complies with its permit, receives proper DEP oversight and fulfills its intended construction purpose rather than functioning as a landfill.
She noted the project is in its 16th year, has accepted roughly two-thirds of the fill originally anticipated and is behind its projected construction schedule.
Ritchey also pointed to DEP’s renewal of a permit allowing slag to be used as fill as a concern because it could allow the project to continue for years beyond its current expiration date.
Project completion
At a recent Palmerton Borough Council meeting, Parrish said the remediation project could be completed within the next two years, though he cautioned that future conditions could affect that time frame.
Impact Environmental is overseeing remediation of the former zinc plant property, where contaminated areas are being capped with an earthen protective layer intended to support future warehouse development. The project is currently in the second of three remediation phases.
Council members questioned Parrish about truck traffic, debris along Route 248, overweight loads and permit time frames.
Councilman Andrew Hollywood noted that four trucks were found to be overweight during a previous site visit and asked about truck-washing procedures.
Parrish said high-quality fill materials are subject to testing.
Residents also voiced concerns about odors, the type of material being brought to the site, truck traffic and the project’s lengthy. Parrish said discussions with potential developers are ongoing and that the western portion of the property has already reached its final elevation.
The site has long been promoted for redevelopment. Parrish said the 120-acre property continues to be marketed to prospective developers with the goal of preparing it for future construction.
Councilman Kris Hoffner noted the permit was originally issued in 2010 and said local officials have repeatedly raised concerns.