Additional work needed on Tamaqua bridge

Additional work is needed on County Bridge 134 on Cedar Street in Tamaqua.

The concrete was damaged more than previously thought necessitating the change commissioners voted for Wednesday.

Previously, 4 inches of concrete was to be removed, but more was needed. The cost is $4,712.50.

Commissioners in December approved $21,100 in improvements from liquid fuels funds to the 89-foot bridge that dates to 1937.