The Pennsylvania Department of Transportation will try to reopen Route 209 one lane at a time rather than wait for the full highway, Secretary Mike Carroll said Tuesday, as crews push into the fourth week of emergency repairs at the site of the Oct. 31 wall collapse.

“We are going to hold to the six to eight weeks,” Carroll said of reopening the road. “I can promise the public that we are working feverishly to come in closer to the six than the eight, but I want to just set expectations in a fair way so folks know. What we will aim to do at the very beginning is at least get one lane open with a temporary signal, so that will get us this roadway reopened sooner rather than later.”

Falling temperatures have become a factor.

“Mother Nature and the calendar are conspiring against us,” Carroll said. “It’s gotten colder since the last time we were here, and anybody who works with concrete knows that cold temperatures result in longer curing times. We don’t have ideal conditions going forward as far as the weather is concerned. But regardless, we will keep at it.”

Crews are installing rock anchors through the weekend and will begin building the foundation for a new wall early next week.

PennDOT District 5 Executive Chris Kufro laid out what comes next. Contractors are excavating for the footing, then will drive micro piles into rock and run anchors horizontally into the mountainside to lock the base in place. A concrete cap goes over the piles and anchors and has to cure before the wall itself can rise.

“They’ll build this reinforced grid wall up from that concrete base, and it’s layers of geotextile material, clean rock in between each layer, and they’ll build it up until they hit the roadway surface,” Kufro said. “And then they’ll restore the roadway to allow traffic.”

Anchor work continues on both sides of the failure, and it is slow.

“There’s a lot of anchors to install, and it takes time to go through the rock,” Kufro said.

Engineers have now flagged two more stretches of wall for reinforcement, one on either side of the collapse.

“To the east, there’s a piece of wall section — we’re going to do a similar repair, steel mesh, shotcrete, rock anchors into that section,” Kufro said. “And also behind me to the west, there’s a small section that we’re also going to be strengthening.”

Both will be repaired while the main wall goes up.

Asked whether the cause of the slide has been determined and whether the repairs will prevent another, Carroll pointed to the age of the structure.

“The original slide was the result of an aged wall over 100 years old and Mother Nature, two very difficult opponents for anybody in government,” he said.

The Reading & Northern Railroad has resumed service and the trail at the base of the slope has reopened, Kufro said. Crews worked with the railroad to repair track and restored fencing along the trail.

No one has been hurt on the job, according to Carroll, who said crews will take Thanksgiving off and return Friday.

“I want all of them to be home with their families for Thanksgiving, to be able to take that day as an important day,” Carroll said. “And then we should all be thankful that they will be back on the job on Friday, resuming work here for the citizens of this region.”

J.D. Eckman Inc. is the prime contractor. Axis Stabilization is handling the slope work.

State Rep. Doyle Heffley, who drove into the backup the morning the wall gave way, said the response began the same day.

“Within a short time, I was texting Secretary Carroll and talking to Chris on the phone, and that evening I think they had engineers out here, really coming up with the game plan,” Heffley said. “There’s one road that connects all of Carbon County. It’s 209. So this is a vital artery, and we’re really excited to see the progress being made, and looking forward to the reopening.”

State Sen. Dave Argall walked the reopened trail over the weekend.

“I live just a couple of miles away, and we are really pleased to see the response,” Argall said.

PennDOT said it will give another update in December.

An excavator works Tuesday at the edge of the Route 209 collapse in Nesquehoning, where crews have covered the slope with steel mesh and shotcrete. Contractors are excavating for the foundation of a new wall and driving rock anchors into the mountainside on both sides of the failure. JARRAD HEDES/TIMES NEWS
A worker walks the trail Tuesday below Route 209, where crews have rebuilt the Reading & Northern Railroad track and reopened the path at the base of the slope. Both were closed after the Oct. 31 wall collapse. JARRAD HEDES/TIMES NEWS
PennDOT Secretary Mike Carroll, right, gives an update Tuesday on repairs to Route 209 as District 5 Executive Chris Kufro listens. Carroll said PennDOT will try to open one lane with a temporary signal rather than wait for the full highway to reopen. JARRAD HEDES/TIMES NEWS