Towamensing adopts data center rules

Towamensing Township enacted a 27-page data center ordinance earlier this month.

Data centers and/or data center campuses will be permitted in HC-heavy commercial and L1-limited industrial zones.

A minimum lot area of 10 acres is required, with front and rear setbacks of 300 feet and side setbacks of 200 feet. The building height must comply with zoning ordinances, which is 8 feet high. A chain-link fence with barbed wire at the top is required.

Noise, water and sewage studies are also among the requirements. “A description of how the recycling or discharge of water will impact surrounding areas in the Township” also is needed.

The location of existing and proposed on-lot sewage disposal systems must be identified as well as aquifer testing plans.

A procedure to follow is spelled out if anyone believes their well has been contaminated.

Electricity expectations are defined to require written confirmation that the electric provider can connect to the facility and has an adequate capacity to supply the service.

Numerous reports are required under the ordinance. They include the effect on wetlands, springs, ephemeral pools and water bodies within 3,000 feet of the property.

Data centers need to provide quarterly reports to the township to include:

• The quantity of all withdrawals, measured by means of a continuous-recording device, flow meter, or other method accurate to within 5% of actual flow.

• Groundwater levels at all monitoring wells, measured on a daily basis.

• Precipitation data, measured on a daily basis or such other frequency as may be approved by the township.

• Certification of the accuracy of all measuring devices and methods to within 5% of actual flow.

• Two entrances and exits are required for emergency vehicles. A Knox Box, which holds a master key for emergency responders must be made available.

• Decommissioning expectations are defined in the ordinance.

For the full data center ordinance contact the township office.