Log In


Reset Password

Sewer project has new timeline L. Towamensing plant slated to bid next April

A bid award for Lower Towamensing Township’s sewer plant project is anticipated by next year.

Doug Kopp, a civil engineer with ARRO Consulting, discussed a new timeline for the sewer project at Tuesday’s board of supervisors meeting.

Kopp noted they are behind schedule on the project’s anticipated timetable.

He told the board they are now projecting a bid award by April 2027.

“That’s aggressive, but that schedule is definitely doable,” Kopp said.

Kopp said they are more than 60% complete, with the exception of the pump station.

“The pump station we are doing needs to be more designed than it’s currently at,” he said.

Kopp provided supervisors with an amendment to amend the previous Professional Services Agreement dated March 29, 2024 between ARRO Consulting Inc. and the township to provide consulting engineering services for the design of a new gravity sanitary sewer system, pump station and force main.

These additional services are to be provided for a not-to-exceed fee of $230,000, an increase in the previous fees for a new not-to-exceed fee of $333,000.

Supervisor Mike Takerer said he thought it wise for the board to wait until all three supervisors are present.

Board Chairman Jay Mullikin was absent.

The board then agreed to table the matter until its March meeting.

The proposed pump station is anticipated to be a submersible pump station with pumps capable of pumping at about 500 gallons per minute, with no building.

The station will be enclosed by a chain-link fence with one light and surface-mounted electrical controls.

Emergency power will be provided by a diesel generator with a fuel tank capable of providing 72 hours of power when full.

The revised schedule is as follows:

• Complete design by May.

• Submit permit applications by June.

• Submit 60% of design by June.

• Receive comments by June.

• Receive permits by November.

• Submit 90% of design by December.

• Submit 100% of design by January 2027.

• Advertise by February 2027.

• Open bids by March 2027.

• Award bid by April 2027.

In August, Kopp told supervisors the next step was to submit for sewer and environmental permits related to sewer and construction.

Kopp said at that time the project’s anticipated timetable was slightly off by a few months.

He said last February that the north and south sides of Little Gap Road would become low pressure.

Kopp said the users would be the same 28 customers who would need grinder pumps.

He said the system savings projection would reduce the cost from $15 million to $13.5 million.

Supervisors then gave Kopp the go-ahead to pursue converting that section from gravity to a grinder pump station.

Kopp said the next step was to pursue permits from various state agencies.

The sewer project has been under consideration for decades. It gained steam under Carbon Engineering in 2022, but stalled. ARRO Consulting took over the project in 2023, but progress was slow as it waited to receive all of the CAD drawings from Carbon Engineering, not knowing if they would have to start the project from the beginning.

Carbon wouldn’t release all of their work because of a payment discrepancy with the township. By March of 2024, ARRO was getting the CAD files it needed.

For ARRO’s part, Kopp told the supervisors in March 2024 that the professional services agreement with them for the work would cost the township $103,000. He told them the township would not be charged anything above that cost, even if there are additional costs for their work.