Looks like Pleasant Valley School District might have an architect for the high school renovation project. A vote will be taken at the school board meeting on Aug. 24.

At their district planning meeting last week, Arif Fazil, the president of D’Huy Engineering Inc., told the school board the Capital Improvements Project committee has selected an architectural firm to handle the renovations. D’Huy was hired by the school district to lead the improvement projects, which will encompass all four school buildings.

The school district is estimating the high school renovation and upgrades to total $88 million.

Fazil said, “Basically, the bottom line is we’re targeting the $88 million; the number was what the board authorized us to target.”

Six architecture firms came out to take a look at the high school, Fazil said. One declined putting in a proposal because it said it has too much work, but five did submit proposals.

Of those five, three were selected for interviews, and KCBA Architects, with offices in Hatfield and Center Valley, was selected. The other two companies were GKO (Godshall Kane O’Rourke) Architects in Ambler and Alloy5 Architecture in Bethlehem.

“The main focus that we were looking at is the qualifications of the individual key members and their consultants, including mechanical, electrical and plumbing, which is almost half the cost of this project,” Fazil said.

The committee also considered how the firms approached the needs of the project, and ideas for how they would integrate solutions.

Fazil said KCBA wasn’t the lowest, but after they reduced their fee, the committee decided to could go with them.

The committee included school board directors Norm Burger, Diane Serfass and President Sue Kresge, as well as the high school principals and D’Huy staff.

“The three finalists all had very good ideas,” Burger said.

Burger said the one that ended up being the preferred choice had worked on the project previously, which didn’t go forward at that time.

“So they actually had a little bit of advantage in the sense that they had more time to be exposed and come up with some excellent drawings, which I think everyone was pleased with,” Burger said.

Serfass said, “The chosen firm really had everything together. They proved to us that they work together as a team, even though they were different subcontractors that they work very well together. That was the deciding factor for me.”

Kresge agreed saying, “They do work well as a team. Each firm brought ideas. … KCBA really showed us they were top notch.”

Fazil said the parameters of the project include utilizing the JC Mills section of the high school, improving and repairing site infrastructure, utilities, and the internal road by extending it to create the loop around the campus.

Fazil said the plans are based on an enrollment of 1,200 students, classroom space for 1,325 students, and 1,425 for core spaces like the cafeteria.

“We don’t want to have to do an extension to that,” he said. “We’re not extending ourselves too much. We’re not too conservative, and we’re not spending money on something that isn’t needed.

The plan is to have a cohesive high school with a focal point and security control. They plan to add space to the weight room, team rooms and cafeteria.

“Other than that, we have too much space,” Fazil said.

They also plan to repurpose the old auditorium and make specific entrance.

Currently, the project is a little ahead of schedule, Fazil said. The design process will take about a year with the project being ready to go out for bid toward the end of 2024. Construction would begin in 2025.

Arif Fazil, the president of D'Huy Engineering Inc., tells the Pleasant Valley School Board that the Capital Improvement Project committee has selected KCBA Architects, with offices in Hatfield and Center Valley, to draw up the designs for renovations to the high school. KRISTINE PORTER/TIMES NEWS