Published March 26. 2015 04:00PM
Crews have started putting the beams in place for the Route 903 bridge project in Jim
Thorpe. The beam delivery schedule for today was postponed due to the weather forecast. As the 59 beams are delivered over the next few weeks, traffic delays are being reported. Beams range in length from 45 to 133 feet and weigh from 20,000 to 150,000 pounds.To see a video of the beams being delivered, visit our Times News Facebook page.